1. Purpose
Define how ACME GmbH plans and executes internal audits to verify QMS conformity, implementation effectiveness, and maintenance.
2. Scope
Applies to all QMS processes and records, including document control, design controls, supplier controls, post-market activities, and management processes.
- Annual audit program
- Process risk and performance data
- Previous audit findings and CAPAs
- Applicable standard/regulatory updates
4. Outputs
- Audit plan, checklist, report, and finding records
- CAPA requests and follow-up evidence
5. Roles and Responsibilities
| Role |
Responsibilities |
| Auditor |
Plans audits, remains independent of the audited activities, and is trained and competent in applicable QMS processes, audit principles, and relevant regulatory requirements. |
| Auditee Process Owner |
Provides evidence and executes corrective actions. |
| QA Lead |
Tracks findings and CAPA integration. |
| Management Representative |
Reviews outcomes and ensures escalation where needed. |
6. Procedure
6.1 Audit Program Planning
- Define annual audit schedule covering all QMS processes within a 12-month cycle.
- Prioritize high-risk/poor-performing processes for increased audit frequency.
- Ensure auditors are independent of the audited activity.
6.2 Audit Preparation
- Define scope, criteria, objectives, and methods in an audit plan.
- Prepare checklist aligned to SOP and ISO clause requirements.
- Notify auditees of audit timing, artifacts needed, and interview expectations.
- Retain the approved audit plan as part of the audit record.
6.3 Audit Execution
- Conduct opening meeting to confirm scope and logistics.
- Collect objective evidence via interviews, record review, and process walkthrough.
- Classify findings as
major, minor, or observation.
- Assess both conformity to defined procedures and effectiveness in achieving intended process outcomes.
6.4 Reporting and Follow-Up
- Issue audit report within 10 business days of audit completion.
- For each nonconformity, require corrective action owner and due date.
- Track closure and effectiveness through CAPA system where applicable.
- Conduct follow-up verification for unresolved or high-risk findings.
6.5 Management Escalation
- Escalate repeated major findings to management review.
- Include audit trends and overdue actions in quarterly quality metrics.
7. Required Records
- Audit plan and checklist
- Audit report and finding log in the designated product/study record repository
- Closure/effectiveness evidence
8. Traceability
| Standard Clause |
Control in this SOP |
| ISO 13485:2016 8.2.4 |
Defines audit planning, independence, criteria, reporting, and follow-up controls. |
- SOP-002 CAPA
- SOP-004 Management Review
- SOP-016 Quality Metrics and Data Analysis
10. Revision History
| Revision |
Revision Date |
Change Summary |
| R00 |
2026-03-01 |
Initial placeholder release. |
| R01 |
2026-03-02 |
Full internal audit planning/execution/follow-up procedure implemented. |
| R02 |
2026-03-05 |
Updated audit record-location control to designated product/study repositories instead of qms-lite local record paths. |
| R03 |
2026-03-07 |
Renamed the controlled audit role to auditor and aligned wording to the simplified small-team role taxonomy. |
| R04 |
2026-03-18 |
Removed top-table standards clause metadata; normative references remain in the Traceability section. |
| R05 |
2026-03-25 |
Added explicit auditor competence expectations, required audit-plan methods/retention, and effectiveness assessment language. |
| R06 |
2026-04-27 |
Renamed YAML metadata field effective_date to revision_date to align controlled-document metadata with the tag-based publication model. The effective date is derived from the published QMS release tag rather than from the document front matter. |